Queens Council District 20 Sidewalk Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct tree pits and sidewalks in Council District 20 in Queens.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2022
Projected Completion Date: February 2023
Completion Date: October 2023 (Design)

Procurement

Start Date: October 2023
Projected Completion Date: October 2024
Completion Date: June 2025 (Procurement)

Construction

Start Date: October 2025
Projected Completion Date: October 2026

Understand how we build parks.

Funding

Total Funding: $500,000
Funding Source: City Council