Riverside Park 105th Street Staircase Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the staircase at West 105th Street in Riverside Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2022
Projected Completion Date: August 2023
Completion Date: December 2023 (Design)

Procurement

Start Date: December 2023
Projected Completion Date: September 2025
Completion Date: June 2025 (Procurement)

Construction

Start Date: August 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $2,700,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Riverside Park, Manhattan
Riverside Drive near West 105th Street
Community Board: 07, 09

 

Project Staff

Project Liaison: Steve Simon