Riverside Park 105th Street Staircase Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the staircase at West 105th Street in Riverside Park.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2022
Projected Completion Date:
August 2023
Completion Date:
December 2023
(Design)
Procurement
Start Date: December 2023
Projected Completion Date:
September 2025
Completion
Date:
June 2025
(Procurement)
Construction
Start Date: August 2025
Projected Completion Date:
August 2026
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Riverside Park, Manhattan
Riverside Drive near West 105th Street
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project