Riverside Park 105th Street Staircase Reconstruction
-
100% complete
-
100% complete
-
2% complete
This project will reconstruct the staircase at West 105th Street in Riverside Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2022
Projected Completion Date:
August 2023
Completion Date:
December 2023
(Design)
Procurement
Start Date: December 2023
Projected Completion Date:
September 2025
Completion
Date:
June 2025
(Procurement)
Construction
Start Date: August 2025
Projected Completion Date:
August 2026
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Riverside Park, Manhattan
Riverside Drive near West 105th Street
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project