Benninger Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will reconstruct Benninger Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2022
Projected Completion Date: April 2023
Completion Date: September 2023 (Design)

Procurement

Start Date: September 2023
Projected Completion Date: September 2024
Completion Date: April 2025 (Procurement)

Construction

Start Date: June 2025
Projected Completion Date: June 2026

Understand how we build parks.

Funding

Total Funding: $3,999,000
Funding Source: City Council

Location

Benninger Playground, Queens
Madison Street between 60th Place and Fresh Pond Road
Community Board: 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project