Captain Tilly Park Goose Pond Restoration
-
100% complete
-
85% complete
-
0% complete
This project will restore the Goose Pond at Captain Tilly Park.
Project Notes
Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
December 2023
Completion Date:
June 2024
(Design)
Procurement
Start Date: June 2024
Projected Completion Date:
March 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Captain Tilly Park, Queens
Highland Avenue, Gothic Drive, Chapin Parkway, 85th Avenue and 165th Street
Community Board: 08