Paerdegat Park Ballfields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the ballfields at Paerdegat Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2021
Projected Completion Date: December 2022
Completion Date: February 2023 (Design)

Procurement

Start Date: February 2023
Projected Completion Date: February 2024
Completion Date: July 2025 (Procurement)

Construction

Start Date: August 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $5,500,000
Funding Source: Mayoral

Location

Paerdegat Park, Brooklyn
Farragut Road between East 40th Street and East 41st Street
Community Board: 17

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project