Hickman Playground Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct Hickman Playground.
Project Notes
Project Update: The project has entered procurement and is being reviewed and prepared for solicitation.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2023
Projected Completion Date:
May 2025
Completion Date:
December 2024
(Design)
Procurement
Start Date: September 2025
Projected Completion Date:
September 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Hickman Playground, Brooklyn
Veterans Avenue between East 66th Street and East 68th Street
Community Board: 18
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project