Daniel Boone Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    5% complete

This project will reconstruct Daniel Boone Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: June 2023 (Design)

Procurement

Start Date: June 2023
Projected Completion Date: September 2025
Completion Date: July 2025 (Procurement)

Construction

Start Date: October 2025
Projected Completion Date: October 2026

Understand how we build parks.

Funding

Total Funding: $8,401,000
Funding Sources:
  • Borough President
  • City Council

Location

Daniel Boone Playground, Bronx
West Farms Road and Boone Avenue
Community Board: 03

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project