Pelham Parkway Malls Partial Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct portions of the Pelham Parkway Malls.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
April 2025
Completion Date:
April 2025
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Pelham Parkway, Bronx
Pelham Parkway between Wallace and Stillwell Avenues
Community Board: 11
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks about this project