Shoelace Park Fitness Equipment Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will construct fitness equipment in Shoelace Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2022
Projected Completion Date: January 2023
Completion Date: January 2023 (Design)

Procurement

Start Date: January 2023
Projected Completion Date: October 2023
Completion Date: February 2025 (Procurement)

Construction

Start Date: August 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $1,711,000
Funding Sources:
  • City Council
  • Mayoral

Location

Bronx River Parkway, Bronx
Bronx Boulevard, East 211th Street and East 229th Street
Community Board: 06, 09, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project