Haffen Park Pool Complex Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the pool complex at Haffen Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2021
Projected Completion Date: October 2022
Completion Date: February 2023 (Design)

Procurement

Start Date: February 2023
Projected Completion Date: April 2026
Completion Date: October 2025 (Procurement)

Construction

Start Date: December 2025
Projected Completion Date: August 2027

Understand how we build parks.

Funding

Total Funding: $14,016,000
Funding Source: Mayoral

Location

Haffen Park, Bronx
1814 Burke Avenue
Community Board: 12

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project