Jerome Playground Reconstruction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct the basketball courts, playground, and track and field in Jerome Playground.
Project Notes
Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date:
July 2023
(Design)
Procurement
Start Date: July 2023
Projected Completion Date:
February 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Jerome Playground, Brooklyn
Wortman Avenue & Warwick Street
Community Board: 05
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project