Jerome Playground Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the basketball courts, playground, and track and field in Jerome Playground.

Project Notes

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: July 2023 (Design)

Procurement

Start Date: July 2023
Projected Completion Date: February 2026
Adjusted Completion Date: December 2025 (Procurement)

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Jerome Playground, Brooklyn
Wortman Avenue & Warwick Street
Community Board: 05

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project