Poe Park Plaza and Playground Reconstruction
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct the plaza and playground in Poe Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2024
Projected Completion Date:
August 2025
Adjusted Completion Date:
May 2026
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Poe Park, Bronx
East 192nd Street, Grand Concourse, and East Kingsbridge Road
Community Board: 07
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks about this project