Old Howard Beach Shoreline Restoration
-
80% complete
-
0% complete
-
0% complete
This project will restore shoreline areas in Old Howard Beach.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2024
Projected Completion Date:
December 2025
Adjusted Completion Date:
July 2026
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bayview Avenue and Broadway near 102nd Street