Crotona Park Green Infrastructure Construction
-
100% complete
-
100% complete
-
0% complete
This project will install green infrastructure within Crotona Park.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2022
Projected Completion Date:
July 2023
Completion Date:
June 2023
(Design)
Procurement
Start Date: June 2023
Projected Completion Date:
June 2024
Completion
Date:
August 2025
(Procurement)
Construction
Start Date: August 2025
Projected Completion Date:
August 2026
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Crotona Park, Bronx
North of Claremont Pkwy and Fulton Ave Intersection
Community Board: 03
Project Staff
Contact NYC Parks about this project