Crotona Park Green Infrastructure Construction
-
100% complete
-
100% complete
-
34% complete
This project will install green infrastructure within Crotona Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2022
Projected Completion Date:
July 2023
Completion Date:
June 2023
(Design)
Procurement
Start Date: June 2023
Projected Completion Date:
June 2024
Completion
Date:
August 2025
(Procurement)
Construction
Start Date: August 2025
Projected Completion Date:
August 2026
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Crotona Park, Bronx
North of Claremont Pkwy and Fulton Ave Intersection
Community Board: 03
Project Staff
Contact NYC Parks about this project