Crotona Park Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    34% complete

This project will install green infrastructure within Crotona Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: July 2023
Completion Date: June 2023 (Design)

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: August 2025 (Procurement)

Construction

Start Date: August 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $514,000
Funding Source: Mayoral

Location

Crotona Park, Bronx
North of Claremont Pkwy and Fulton Ave Intersection
Community Board: 03

 

Project Staff

Contact NYC Parks about this project