Crotona Park Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will install green infrastructure within Crotona Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: July 2023
Completion Date: June 2023 (Design)

Procurement

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: August 2025 (Procurement)

Construction

Start Date: August 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $514,000
Funding Source: Mayoral