Van Cortlandt Park Forest Tree Replacement
-
100% complete
-
100% complete
-
1% complete
This project will plant replacement trees and restore native species habitat within forested natural areas in Van Cortlandt Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2022
Projected Completion Date:
March 2023
Completion Date:
March 2023
(Design)
Procurement
Start Date: March 2023
Projected Completion Date:
March 2024
Completion
Date:
February 2025
(Procurement)
Construction
Start Date: September 2025
Projected Completion Date:
August 2028
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Van Cortlandt Park, Bronx
South of Forest Ave between Broadway and Major Deegan Expressway
Community Board: 07, 08, 12