Marcus Garvey Park Pelham Fritz Recreation Center Roof Reconstruction
-
35% complete
-
0% complete
-
0% complete
This project will reconstruct the roof at Pelham Fritz Recreation Center in Marcus Garvey Park.
Project Notes
Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.
Project Timeline
Design
Assigned & Start Date: October 2022
Projected Completion Date:
December 2023
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral