Shore Park Parkway Promenade and 4th Avenue Entrance Greenway Reconstruction
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct the promenade, greenway and 4th Avenue greenway entrance.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2023
Projected Completion Date:
May 2025
Adjusted Completion Date:
June 2026
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
- Private
Location
Shore Park and Parkway, Brooklyn
Shore Parkway Greenway West Between Bay Ridge Avenue and 4th Avenue Greenway Entrance
Community Board: 10
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project