Leif Ericson Park Greenway Construction
-
50% complete
-
0% complete
-
0% complete
This project will construct a greenway at Leif Ericson Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
April 2025
Adjusted Completion Date:
April 2026
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
- Private
Location
Leif Ericson Park, Brooklyn
67th Street, 66th Street between 2nd Avenue and 7th Avenue
Community Board: 10