Leif Ericson Park Greenway Construction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a greenway at Leif Ericson Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: April 2025
Adjusted Completion Date: April 2026 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Borough President
  • Mayoral
  • Private

Location

Leif Ericson Park, Brooklyn
67th Street, 66th Street between 2nd Avenue and 7th Avenue
Community Board: 10

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project