St. Michael's Playground Reconstruction
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct the children's play area, handball courts and basketball courts at St. Michael's Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2024
Projected Completion Date:
October 2025
Adjusted Completion Date:
January 2026
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Private
Location
St. Michael's Playground, Queens
This project is located between the Brooklyn Queens Expressway, and 30th Avenue and 31st Avenue.
Community Board: 01
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project