St. Michael's Playground Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the children's play area, handball courts and basketball courts at St. Michael's Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2024
Projected Completion Date: October 2025
Adjusted Completion Date: January 2026 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Borough President
  • City Council
  • Private

Location

St. Michael's Playground, Queens
This project is located between the Brooklyn Queens Expressway, and 30th Avenue and 31st Avenue.
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project