Lawrence Virgilio Playground and Mini Pool Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Lawrence Virgilio Playground and the mini pool.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2024
Projected Completion Date: October 2025
Adjusted Completion Date: January 2026 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Borough President
  • City Council

Location

Lawrence Virgilio Playground, Queens
52nd Street and Woodside Avenue between 39th Road and 39th Drive
Community Board: 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project