Rolph Henry Playground Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct Rolph Henry Playground.
Project Notes
Project Update: The project has entered procurement and is being reviewed and prepared for solicitation.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date:
July 2025
(Design)
Procurement
Start Date: January 2026
Projected Completion Date:
January 2027
Adjusted Completion
Date:
August 2025
(Procurement)
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Rolph Henry Playground, Brooklyn
Clarkson Avenue & New York Avenues
Community Board: 09
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project