St. Andrew's Playground Reconstruction and Public Restroom Building Construction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the park and construct a new public restroom building at St. Andrew's Playground.

Project Notes

Project Update: Parks is continuing to develop the documents to build this project.

Project Timeline

Design

Assigned & Start Date: January 2026
Projected Completion Date: May 2026

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

St. Andrew's Playground, Brooklyn
Atlantic Avenue, Herkimer Street, Kingston Avenue and St. Andrew's Place
Community Board: 03

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project