Washington Park Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct Washington Park, including play equipment, safety surface, spray shower, ADA accessible basketball court with bleachers, passive open area with benches and tables, water and drainage systems, park security lighting, fencing, pavements and landscaping.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: October 2024
Projected Completion Date:
January 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Washington Park, Bronx
East 183rd Street between Washington Avenue and Park Avenue
Community Board: 06
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks about this project