Mellett Playground Multi-Purpose Play Area and Handball Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the basketball and handball courts and construct new pickleball courts, synthetic turf and walking track in Mellett Playground.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2022
Projected Completion Date: December 2023
Completion Date: May 2024 (Design)

Procurement

Start Date: May 2024
Projected Completion Date: April 2026
Completion Date: October 2025 (Procurement)

Construction

Start Date: November 2025
Projected Completion Date: November 2026

Understand how we build parks.

Funding

Total Funding: $2,600,000
Funding Sources:
  • City Council
  • Mayoral

Location

Mellett Playground, Brooklyn
Avenue V between East 13th Street and East 14th Street
Community Board: 15

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project