Oracle Playground Reconstruction
-
100% complete
-
40% complete
-
0% complete
This project will reconstruct Oracle Playground.
Project Notes
Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.
Project Timeline
Design
Assigned & Start Date: May 2023
Projected Completion Date:
June 2024
Completion Date:
July 2024
(Design)
Procurement
Start Date: May 2025
Projected Completion Date:
May 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Oracle Playground, Brooklyn
121 Adelphi Street between Park and Myrtle Avenues
Community Board: 02
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project