Oracle Playground Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct Oracle Playground.
Project Notes
Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.
Project Timeline
Design
Assigned & Start Date: May 2023
Projected Completion Date:
June 2024
Completion Date:
July 2024
(Design)
Procurement
Start Date: May 2025
Projected Completion Date:
May 2026
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Oracle Playground, Brooklyn
121 Adelphi Street between Park and Myrtle Avenues
Community Board: 02
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project