Givans Creek Woods Park Pathway Construction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a pathway at Givans Creek Woods Park.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: July 2025
Completion Date: August 2025 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Givans Creek Woods, Bronx
Co-op City Boulevard between Baychester Avenue and Dreiser Loop
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project