Hutchinson River Parkway District 10 Headquarters Construction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a headquarters for Bronx M&O District 10 at Hutchinson River Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2024
Projected Completion Date: September 2025
Adjusted Completion Date: April 2026 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Hutchinson River Parkway, Bronx
Hutchinson River Parkway East, Continental Avenue and East 197th Street
Community Board: 10, 11

 