De Witt Clinton Park Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct De Witt Clinton Park.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: June 2025
Projected Completion Date:
July 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
De Witt Clinton Park, Manhattan
De Witt Clinton Playground in De Witt Clinton Park on the 12th Ave side between West 52nd Street and West 54th Streets
Community Board: 04
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project