De Witt Clinton Park Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct De Witt Clinton Park.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: June 2025
Projected Completion Date: July 2026

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • City Council
  • Mayoral

Location

De Witt Clinton Park, Manhattan
De Witt Clinton Playground in De Witt Clinton Park on the 12th Ave side between West 52nd Street and West 54th Streets
Community Board: 04

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project