St. Nicholas Playground South Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct St. Nicholas Playground South.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2024
Projected Completion Date: December 2025
Adjusted Completion Date: May 2026 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Borough President
  • Mayoral

Location

St. Nicholas Playground South, Manhattan
Adam Clayton Powell Jr. Boulevard between West 127th and West 129th Streets
Community Board: 10

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project