Ferry Point Playground Reconstruction
-
100% complete
-
100% complete
-
7% complete
This project will reconstruct the playground in Ferry Point Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2022
Projected Completion Date:
October 2023
Completion Date:
November 2023
(Design)
Procurement
Start Date: November 2023
Projected Completion Date:
November 2024
Completion
Date:
February 2025
(Procurement)
Construction
Start Date: July 2025
Projected Completion Date:
July 2026
Understand how we build parks.
Funding
Funding Source: City Council
Location
Ferry Point Park, Bronx
Balcom Avenue and Dewey Avenue.
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome