  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    7% complete

This project will reconstruct the playground in Ferry Point Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2022
Projected Completion Date: October 2023
Completion Date: November 2023 (Design)

Procurement

Start Date: November 2023
Projected Completion Date: November 2024
Completion Date: February 2025 (Procurement)

Construction

Start Date: July 2025
Projected Completion Date: July 2026

Understand how we build parks.

Funding

Total Funding: $3,122,000
Funding Source: City Council

Location

Ferry Point Park, Bronx
Balcom Avenue and Dewey Avenue.
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project