Shore Front Parkway Roller Hockey Rink Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the roller hockey rink along Shore Front Parkway at Rockaway Beach.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2023
Projected Completion Date: May 2025
Adjusted Completion Date: September 2025 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Rockaway Beach Boardwalk, Queens
Shore Front Parkway at Beach 109th Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower