Shore Front Parkway Roller Hockey Rink Reconstruction
-
50% complete
-
0% complete
-
0% complete
This project will reconstruct the roller hockey rink along Shore Front Parkway at Rockaway Beach.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2023
Projected Completion Date:
May 2025
Adjusted Completion Date:
September 2025
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Rockaway Beach Boardwalk, Queens
Shore Front Parkway at Beach 109th Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project