Queens Tree-Damaged Sidewalk Reconstruction Community Boards 1-6,9,10 (QG-1223MR)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Community Boards 1-6,9, 10.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

The average time for design is 9-14 months. The design timeline for this specific contract will be established once the project scope is determined.

Procurement

Start Date:
Completion Date: September 2022 (Procurement)

Construction

Start Date: May 2022
Projected Completion Date: April 2024
Completion Date: November 2023

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Various locations, Queens West