Bushwick Inlet Park Sewer Connection Construction
-
100% complete
-
100% complete
-
100% complete
This project will install a sewer connection in Bushwick Inlet Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2023
Projected Completion Date:
February 2024
Completion Date:
July 2023
(Design)
Procurement
Start Date: July 2023
Projected Completion Date:
July 2024
Completion
Date:
January 2025
(Procurement)
Construction
Start Date: May 2025
Projected Completion Date:
November 2025
Completion Date: August 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bushwick Inlet Park, Brooklyn
Kent Avenue between N.12th and N.11th Streets
Community Board: 01