Riverside Park Soldiers' and Sailors' Monument Restoration

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will restore the Soldiers' and Sailors' Monument in Riverside Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: June 2025
Adjusted Completion Date: December 2025 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Riverside Park, Manhattan
Riverside Park at West 89th street
Community Board: 07, 09

 