J. Hood Wright Park Retaining Wall and Pedestrian Ramp Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct a retaining wall and pedestrian ramp at J. Hood Wright Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2021
Projected Completion Date: May 2022
Completion Date: November 2023 (Design)

Procurement

Start Date: November 2023
Projected Completion Date: July 2025
Completion Date: July 2025 (Procurement)

Construction

Start Date: October 2025
Projected Completion Date: October 2026

Understand how we build parks.

Funding

Total Funding: $2,954,000
Funding Source: Mayoral

Location

J. Hood Wright Park, Manhattan
South Pinehurst Avenue at West 176th Street
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project