Delphin H. Greene Playground Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct Delphin H. Greene Playground.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: June 2025
Projected Completion Date:
July 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Delphin H. Greene Playground, Queens
121 Avenue between 235 Street and 237 Street
Community Board: 13