Brookville Park Basketball Court Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the Basketball Court at Brookville Park.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: March 2025
Projected Completion Date: June 2026

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Borough President

Location

Brookville Park, Queens
This project is located between South Conduit Avenue, 147th Avenue, 232nd Avenue and Brookville Boulevard
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project