Wolfe's Pond Park Playground Reconstruction and Pickleball Courts Construction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the playground and construct the pickleball courts at Wolfe's Pond Park.

Project Notes

Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.

Project Timeline

Design

Assigned & Start Date: December 2024
Projected Completion Date: March 2026

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Borough President
  • City Council

Location

Wolfe's Pond Park, Staten Island
Cornelia and Chester Avenues
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project