Colden Playground Reconstruction
-
50% complete
-
0% complete
-
0% complete
This project will reconstruct the playground, multipurpose play area, handball courts, basketball court, sidewalks, and security lighting in Colden Playground.
Project Notes
Project Update: Parks is continuing to develop the documents to build this project.
Project Timeline
Design
Assigned & Start Date: November 2024
Projected Completion Date:
February 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Colden Playground, Queens
31st Drive between Union Street and 140th Street
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project