Eae J. Mitchell Park Reconstruction
-
35% complete
-
0% complete
-
0% complete
This project will reconstruct the plaza in Eae J. Mitchell Park.
Project Notes
Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.
Project Timeline
Design
Assigned & Start Date: January 2025
Projected Completion Date:
January 2026
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Eae J Mitchell Park, Bronx
E. 174th Street and Longfellow Avenue
Community Board: 03