Brooklyn Street Tree Planting FY24 - Community Board 11, 13, 15
-
100% complete
-
60% complete
-
0% complete
This project will plant new and replacement trees in Community Boards 11, 13, 15 in Brooklyn.
Project Notes
Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
June 2024
Completion Date:
August 2024
(Design)
Procurement
Start Date: October 2024
Projected Completion Date:
October 2025
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private