Brooklyn Street Tree Planting FY24 - Community Board 7 & 10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    22% complete

This project will plant new and replacement trees in Community Boards 7 & 10 in Brooklyn.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: June 2024
Completion Date: April 2024 (Design)

Procurement

Start Date: April 2024
Projected Completion Date: April 2025
Completion Date: June 2025 (Procurement)

Construction

Start Date: August 2025
Projected Completion Date: August 2026

Understand how we build parks.

Funding

Total Funding: $999,000
Funding Sources:
  • City Council
  • Mayoral