Staten Island Street Tree Planting FY24
-
100% complete
-
100% complete
-
0% complete
This project will plant new and replacement street trees in Staten Island.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
June 2024
Completion Date:
April 2024
(Design)
Procurement
Start Date: April 2024
Projected Completion Date:
August 2025
Completion
Date:
July 2025
(Procurement)
Construction
Start Date: January 2026
Projected Completion Date:
January 2028
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private