East River Playground Reconstruction
-
90% complete
-
0% complete
-
0% complete
This project will reconstruct East River Playground.
Project Notes
Project Update: All contract documents are now in final review to complete the design process.
Project Timeline
Design
Assigned & Start Date: February 2025
Projected Completion Date:
September 2025
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
East River Playground, Manhattan
FDR Drive between E. 106th Street and E. 107th Drive
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks about this project