Hattie Carthan Playground Reconstruction
-
50% complete
-
0% complete
-
0% complete
This project will reconstruct Hattie Carthan Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2025
Projected Completion Date:
August 2025
Adjusted Completion Date:
August 2026
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Hattie Carthan Playground, Brooklyn
Monroe Street between Marcy Avenue and Tompkins Avenue
Community Board: 03
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project