Hattie Carthan Playground Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Hattie Carthan Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2025
Projected Completion Date: August 2025
Adjusted Completion Date: August 2026 (Design)

Procurement

Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Hattie Carthan Playground, Brooklyn
Monroe Street between Marcy Avenue and Tompkins Avenue
Community Board: 03

 

Project Staff

Project Liaison: James Morris
Contact NYC Parks about this project