Harding Park Playground Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct the playground at the north parcel of Harding Park and construct a pump track and passive areas at the undeveloped south parcel.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
Project Timeline
Design
Assigned & Start Date: August 2024
Projected Completion Date:
November 2025
Completion Date:
December 2025
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Harding Park, Bronx
Bolton Avenue between O’Brien and Cornell Avenues
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks about this project