Lou Lodati Playground and Dog Run Reconstruction
-
50% complete
-
0% complete
-
0% complete
This project will reconstruct the playground and the dog run at Lou Lodati Playground.
Project Notes
Project Update: Parks is continuing to develop the documents to build this project.
Project Timeline
Design
Assigned & Start Date: August 2024
Projected Completion Date:
November 2025
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Torsney Playground, Queens
41-15 Skillman Avenue, QUEENS, NY 11104
Community Board: 02
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks about this project