Bensonhurst Park MPPA Reconstruction
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct the MPPA area in Bensonhurst Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2024
Projected Completion Date:
December 2025
Adjusted Completion Date:
March 2026
(Design)
Procurement
Start Date: To Be Determined
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be
established at the conclusion of the design phase.
Construction
Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract
will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Bensonhurst Park, Brooklyn
Cropsey Avenue between 21st Avenue and Bay Parkway
Community Board: 11
Project Staff
Project Liaison: James Morris
Contact NYC Parks about this project