Tudor Park Adult Fitness Equipment Construction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct the adult fitness equipment at Tudor Park.

Project Notes

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: December 2024
Completion Date: December 2024 (Design)

Procurement

Start Date:

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • City Council
  • Mayoral

Location

Tudor Park, Queens
LOCATED BETWEEN NORTH CONDUIT AND 133RD AVENUES AND 83RD STREET
Community Board: 10

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project