Noble Playground Water Service Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the water tap and water service to the basketball courts at Noble Playground.

Project Notes

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Assigned & Start Date: March 2024
Projected Completion Date: February 2025
Completion Date: February 2025 (Design)

Procurement

Start Date:

Construction

Start Date: To Be Determined
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Noble Playground, Bronx
Noble Avenue, Cross Bronx Expressway, and Bronx River Parkway
Community Board: 09

 